Brazil’s Critical Minerals Fund has backed the Colossus rare earths project in Minas Gerais. Viridis reported receipt of a second equity tranche under its US$30 million agreement with ORE Investments and Régia Capital. [1] [4]
Where the money stands
Transaction record
The ASX filing identifies Viridis as the fund’s inaugural investment and confirms the second tranche reported by Mining Weekly. The first tranche came from ORE and Régia in November 2025. The fund is providing the second tranche and the remaining US$20 million. [1] [2]
| Item | Disclosed figure | Status or basis |
|---|---|---|
| First tranche | US$5m | Received in November 2025 |
| Second tranche | US$5m | Receipt disclosed on 16 November 2026 |
| Remaining tranche funding | US$20m | To be funded under the agreement |
| New ordinary shares | 2,080,125 | Issued to settle tranche two |
| Share issue price | A$3.40 | 17% above the last closing price, per Viridis |
| Implied issue value | A$7,072,425 | Shares issued × issue price |
US$ denotes U.S. dollars, A$ Australian dollars, and R$ Brazilian reais. Transaction figures follow the issuer’s filing. [1]
What comes next for Colossus
Project capital and indicative funding mix
US$449m development capital
- Senior debt · ~70% · ~US$314m
- Equity · ~30% · ~US$135m
Assessment. The second tranche shows the fund has begun deploying capital to Colossus. Viridis estimates about US$141m in pro forma cash and equity funding against about US$133m of remaining equity needs. The US$141m includes outstanding proceeds subject to conditions. Senior debt and permitting remain pivotal to management’s 2028 production target. [1]
| Milestone | Evidence to watch for |
|---|---|
| Equity receipts | Confirmation of the remaining US$20m from the fund and of the separate OneIM second tranche, which Viridis says is subject to Australian foreign-investment approval. |
| Senior debt | Executed financing terms and conditions for drawing funds. |
| Licensing and construction | Permit decisions, procurement progress and updates to the 2028 production target. |
| Rare earth separation | Implementation milestones for the Solvay offtake and plans for separation capacity in Brazil. |
Colossus resource update
Mining Weekly’s video provides background on the project’s rare earth resource estimate.
Source register
- Viridis Mining and Minerals, 16 November 2026. ASX announcement and cleansing notice (PDF).
- Mining Weekly, 18 November 2026. Reporting on the second tranche.
- BNDES. 2025 annual report (PDF). The fund’s target capital and cornerstone limits provide context for the issuer-reported commitment figures.
- Viridis Mining and Minerals. Colossus project profile.