Haib’s next test is delivery
Koryx Copper says its Haib pre-feasibility study exceeded expectations. The proposed project now faces the work of securing finance, completing engineering and obtaining permits.
Study results released 17 November 2026 · Development project · Company-reported projections
Haib drilling, 2025. Photo courtesy of Koryx Copper.
A copper-price-dependent case
After-tax NPV₈ by copper-price case
| Metric | Base case | Higher price |
|---|---|---|
| Copper, US$/t | 11,023 | 13,000 |
| NPV₈, US$bn | 2.538 | 3.875 |
| IRR | 24.9% | 32.2% |
| Payback, years | 3.9 | 3.5 |
Base assumptions include US$5/lb copper, US$3,500/oz gold and US$22/lb molybdenum. All values are study estimates. Koryx PFS release
Early output and lifetime averages
Annual output · thousand tonnes
Unit costs · US$/lb payable copper
The revised design routes production through milling and flotation, with heap leaching removed. Coarse gangue rejection reduces the mass entering subsequent flotation. Higher-grade feed is prioritized early in the plan. Project overview
Southern Namibia, near the Orange River
Approximate project reference point, 28°41′48″S, 17°52′59″E. Map © OpenStreetMap contributors. Open full map
Location verified
The supplied alert’s coordinates, −22.561, 17.066, identify the Windhoek area. Haib is in the far south, approximately 12–15 km east of the B1 highway.
The map uses the technical report’s project reference point. It marks an approximate location rather than a surveyed licence boundary.
The next decisions
| Workstream | Company target | Evidence to watch |
|---|---|---|
| Definitive feasibility | Completion during 2027 | Engineering scope and revised costs |
| Permitting | Key approvals by mid-2027 | Issued mining and environmental approvals |
| Early works | Late 2027 | Funding commitments and contracts |
| Main construction | Q1 2028 | Board decision and financing close |
Targets reflect management’s stated schedule. Engineering News / Mining Weekly coverage
Editorial assessment. The central execution questions are whether the financing package supports the capital requirement and whether permitting and infrastructure progress fast enough to meet the proposed schedule.
Watch the Haib PFS briefing
Company-produced presentation listed 17 November 2026. Internet access required for video and map. Watch on YouTube · Official media page
Read the underlying evidence
- Koryx PFS results, 17 November 2026 — primary economics and operating projections.
- Koryx Haib project overview — process design, project context and photography.
- Mining Weekly coverage — management’s assessment and development schedule.
Prepared 18 November 2026. Sector classification updated to mining and minerals. Corporate logo identifies the company covered. NPV means net present value, IRR means internal rate of return, and PFS means pre-feasibility study.