🇳🇦 Haib Copper PFS Exceeds Koryx Expectations as Namibia Project Advances

Haib Copper PFS | panafrican.email

panafrican.email
Mining & Industrial Intelligence
Namibia · Copper / Molybdenum / Gold · 18 November 2026

Haib’s next test is delivery

Koryx Copper says its Haib pre-feasibility study exceeded expectations. The proposed project now faces the work of securing finance, completing engineering and obtaining permits.

Study results released 17 November 2026 · Development project · Company-reported projections

Drilling operations in the arid hills of the Haib copper project, Namibia

Haib drilling, 2025. Photo courtesy of Koryx Copper.

US$2.54bnAfter-tax NPV at 8%
24.9%After-tax IRR
US$2.06bnUpfront capital
24 yearsPlanned processing life

Study economics

A copper-price-dependent case

After-tax NPV₈ by copper-price case

01234US$ billion2.5383.875$11,023/t$13,000/tAssumed copper price

Two published scenarios. The dashed connector guides the eye. PFS financial table
Published post-tax scenarios
Metric Base case Higher price
Copper, US$/t 11,023 13,000
NPV₈, US$bn 2.538 3.875
IRR 24.9% 32.2%
Payback, years 3.9 3.5

Base assumptions include US$5/lb copper, US$3,500/oz gold and US$22/lb molybdenum. All values are study estimates. Koryx PFS release

Operating model

Early output and lifetime averages

Annual output · thousand tonnes

Gross CuEq · years 1–10

145

Gross CuEq · mine life

117

Payable Cu · years 1–10

130

Payable Cu · mine life

105

CuEq combines metals by value. Payable Cu reflects copper credited under sales terms. PFS production highlights

Unit costs · US$/lb payable copper

C1 · years 1–10

1.72

C1 · mine life

2.19

AISC · years 1–10

2.07

AISC · mine life

2.52

C1 includes by-product credits. AISC adds royalties, levies and sustaining capital under Koryx’s definition. PFS cost tables

The revised design routes production through milling and flotation, with heap leaching removed. Coarse gangue rejection reduces the mass entering subsequent flotation. Higher-grade feed is prioritized early in the plan. Project overview

Geography

Southern Namibia, near the Orange River

Approximate project reference point, 28°41′48″S, 17°52′59″E. Map © OpenStreetMap contributors. Open full map

Location verified

The supplied alert’s coordinates, −22.561, 17.066, identify the Windhoek area. Haib is in the far south, approximately 12–15 km east of the B1 highway.

The map uses the technical report’s project reference point. It marks an approximate location rather than a surveyed licence boundary.

NI 43-101 location reference, section 4.1

Delivery watch

The next decisions

Workstream Company target Evidence to watch
Definitive feasibility Completion during 2027 Engineering scope and revised costs
Permitting Key approvals by mid-2027 Issued mining and environmental approvals
Early works Late 2027 Funding commitments and contracts
Main construction Q1 2028 Board decision and financing close

Targets reflect management’s stated schedule. Engineering News / Mining Weekly coverage

Editorial assessment. The central execution questions are whether the financing package supports the capital requirement and whether permitting and infrastructure progress fast enough to meet the proposed schedule.

Company presentation

Watch the Haib PFS briefing

Company-produced presentation listed 17 November 2026. Internet access required for video and map. Watch on YouTube · Official media page

Source register

Read the underlying evidence

  1. Koryx PFS results, 17 November 2026 — primary economics and operating projections.
  2. Koryx Haib project overview — process design, project context and photography.
  3. Mining Weekly coverage — management’s assessment and development schedule.

Prepared 18 November 2026. Sector classification updated to mining and minerals. Corporate logo identifies the company covered. NPV means net present value, IRR means internal rate of return, and PFS means pre-feasibility study.

panafrican.email · Mining & Industrial Intelligence


Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

error: Content is protected !!

Discover more from panafrican.email

Subscribe now to keep reading and get access to the full archive.

Continue reading