What the permit changes
Ucore reports that the Louisiana Department of Environmental Quality issued a minor-source air permit covering construction, testing, commissioning and operation. The classification concerns potential emissions relative to Title V thresholds. Ucore identifies this as the last LDEQ permit needed before it can install enhanced Machine A. The signed permit and its emissions limits, monitoring obligations and other operating conditions remain unverified in this briefing. [1] [3]
From first module to full scale
Annual processing capacity
Project milestone timeline
- · Feedstock arrival announcedUcore reported receiving more than 50 tonnes of mixed rare earth carbonate for commissioning. [2]
- · Permit receipt announcedUcore disclosed the Louisiana air permit number and scope. [1]
- H1 2027 · Commissioning targetUcore plans to commission enhanced Machine A. [1]
Where Louisiana fits in the supply chain
- Feedstock →Mixed rare earth carbonate or oxide enters the plant.
- Separation →RapidSX separates rare earth elements in Alexandria.
- ProductsUcore’s product list includes neodymium-praseodymium (NdPr), samarium, gadolinium and yttrium.
A commercial separation plant in Louisiana could give miners and recyclers another route to market. For African rare earth developers, the markers to watch are qualified feedstock specifications and binding purchase contracts. Ucore identified the initial commissioning material as North American. The disclosures cited here identify no African supplier to the Louisiana project. [1] [2]
Evidence and watchpoints
| Signal | Evidence | What to watch |
|---|---|---|
| Air permit | Ucore announced receipt of permit 2360-00177-00. [1] | Signed LDEQ permit, effective date, emissions limits and monitoring requirements. [3] |
| Commissioning feed | Ucore reported delivery of more than 50 tonnes of North American mixed rare earth carbonate. [2] | Additional feed deliveries and acceptance testing across feed types. |
| Machine A | 600 tonnes per year of planned TREO processing capacity with an H1 2027 commissioning target. [1] | Installation, achieved throughput, product purity and customer qualification. |
| Full build-out | Approximately 9,600 tonnes per year under the scope Ucore describes. [1] | Funding commitments, schedule for additional modules and binding offtake volumes. |
Multimedia
Inside RapidSX
Source register
- Ucore air permit announcement · 17 November 2026 · Company disclosure.
- Ucore commissioning feedstock announcement · 9 November 2026 · Company disclosure.